Budget
House construction cost calculator
Put in the area, the floors and the finish. You get the rate, the split and the material.
Estimated cost to build
Rs. 74,37,960
Rs. 1,652.88 per sq.ft · 4,500 sq.ft built-up · Standard finish
Material
Rs. 58,62,960
Labour
Rs. 15,75,000
Floor by floor
| Level | Area | Rate factor | Cost |
|---|---|---|---|
| Ground floor | 1,125 sq.ft | ×1.00 | Rs. 19,17,000 |
| First floor | 1,125 sq.ft | ×0.95 | Rs. 18,21,150 |
| Second floor | 1,125 sq.ft | ×0.95 | Rs. 18,21,150 |
| Third floor | 1,125 sq.ft | ×0.98 | Rs. 18,78,660 |
| Total | Rs. 74,37,960 | ||
Where the money goes
Across the built work — Rs. 74,37,960. Lump sums like a lift or a borewell are listed above instead.
- Cement Rs. 11,90,073.60 16%
- Steel (TMT) Rs. 10,41,314.40 14%
- Sand Rs. 5,95,036.80 8%
- Aggregate Rs. 4,46,277.60 6%
- Bricks / blocks Rs. 7,43,796 10%
- Doors, windows and fittings Rs. 11,15,694 15%
- Flooring, plaster and paint Rs. 11,15,694 15%
- Electrical Rs. 5,95,036.80 8%
- Plumbing and sanitary Rs. 5,95,036.80 8%
Rates in this district run from Rs. 1,420 to Rs. 2,556 per sq.ft depending on the finish. Yours is Rs. 1,704.
Roughly what it takes
Site thumb rules on 4,500 sq.ft. Useful for checking a supplier's bill, not for ordering against.
1,800 bags
Cement
18,000 kg
Steel (TMT)
8,100 cft
Sand
6,075 cft
Aggregate
36,000 nos
Bricks