Back

Budget

House construction cost calculator

Put in the area, the floors and the finish. You get the rate, the split and the material.

Sets a starting rate. You can type your own below.

Finish
More options

Leave blank to use Rs. 1,420 before the finish multiplier.

Only splits the total into material and labour. It does not change it.

Advanced settings

Finish multipliers

Floor multipliers

Cost shares

Re-scaled to add up to 100% when you save.

Lump sums

Reset to defaults
Start over

Estimated cost to build

Rs. 28,62,720

Rs. 1,704 per sq.ft · 1,680 sq.ft built-up · Standard finish

Material

Rs. 22,74,720

Labour

Rs. 5,88,000

Floor by floor

Level Area Rate factor Cost
Ground floor 1,680 sq.ft ×1.00 Rs. 28,62,720
Total Rs. 28,62,720

Where the money goes

Across the built work — Rs. 28,62,720. Lump sums like a lift or a borewell are listed above instead.

  • Cement Rs. 4,58,035.20 16%
  • Steel (TMT) Rs. 4,00,780.80 14%
  • Sand Rs. 2,29,017.60 8%
  • Aggregate Rs. 1,71,763.20 6%
  • Bricks / blocks Rs. 2,86,272 10%
  • Doors, windows and fittings Rs. 4,29,408 15%
  • Flooring, plaster and paint Rs. 4,29,408 15%
  • Electrical Rs. 2,29,017.60 8%
  • Plumbing and sanitary Rs. 2,29,017.60 8%

Rates in this district run from Rs. 1,420 to Rs. 2,556 per sq.ft depending on the finish. Yours is Rs. 1,704.

Roughly what it takes

Site thumb rules on 1,680 sq.ft. Useful for checking a supplier's bill, not for ordering against.

672 bags

Cement

6,720 kg

Steel (TMT)

3,024 cft

Sand

2,268 cft

Aggregate

13,440 nos

Bricks

This is an estimate, not a quotation. It is worked out from Rs. 1,420 per sq.ft ×1.20 for standard finish. Soil, access, the shape of the plot and the market that month all move the real figure. Send it to us and we will price your actual plot.