Back

Budget

House construction cost calculator

Put in the area, the floors and the finish. You get the rate, the split and the material.

Sets a starting rate. You can type your own below.

Finish
More options

Leave blank to use Rs. 1,420 before the finish multiplier.

Only splits the total into material and labour. It does not change it.

Advanced settings

Finish multipliers

Floor multipliers

Cost shares

Re-scaled to add up to 100% when you save.

Lump sums

Reset to defaults
Start over

Estimated cost to build

Rs. 9,63,612

Rs. 1,661.40 per sq.ft · 580 sq.ft built-up · Standard finish

Material

Rs. 7,60,612

Labour

Rs. 2,03,000

Floor by floor

Level Area Rate factor Cost
Ground floor 290 sq.ft ×1.00 Rs. 4,94,160
First floor 290 sq.ft ×0.95 Rs. 4,69,452
Total Rs. 9,63,612

Where the money goes

Across the built work — Rs. 9,63,612. Lump sums like a lift or a borewell are listed above instead.

  • Cement Rs. 1,54,177.92 16%
  • Steel (TMT) Rs. 1,34,905.68 14%
  • Sand Rs. 77,088.96 8%
  • Aggregate Rs. 57,816.72 6%
  • Bricks / blocks Rs. 96,361.20 10%
  • Doors, windows and fittings Rs. 1,44,541.80 15%
  • Flooring, plaster and paint Rs. 1,44,541.80 15%
  • Electrical Rs. 77,088.96 8%
  • Plumbing and sanitary Rs. 77,088.96 8%

Rates in this district run from Rs. 1,420 to Rs. 2,556 per sq.ft depending on the finish. Yours is Rs. 1,704.

Roughly what it takes

Site thumb rules on 580 sq.ft. Useful for checking a supplier's bill, not for ordering against.

232 bags

Cement

2,320 kg

Steel (TMT)

1,044 cft

Sand

783 cft

Aggregate

4,640 nos

Bricks

This is an estimate, not a quotation. It is worked out from Rs. 1,420 per sq.ft ×1.20 for standard finish. Soil, access, the shape of the plot and the market that month all move the real figure. Send it to us and we will price your actual plot.