Budget
House construction cost calculator
Put in the area, the floors and the finish. You get the rate, the split and the material.
Estimated cost to build
Rs. 9,20,160
Rs. 1,704 per sq.ft · 540 sq.ft built-up · Standard finish
Material
Rs. 7,31,160
Labour
Rs. 1,89,000
Floor by floor
| Level | Area | Rate factor | Cost |
|---|---|---|---|
| Ground floor | 540 sq.ft | ×1.00 | Rs. 9,20,160 |
| Total | Rs. 9,20,160 | ||
Where the money goes
Across the built work — Rs. 9,20,160. Lump sums like a lift or a borewell are listed above instead.
- Cement Rs. 1,47,225.60 16%
- Steel (TMT) Rs. 1,28,822.40 14%
- Sand Rs. 73,612.80 8%
- Aggregate Rs. 55,209.60 6%
- Bricks / blocks Rs. 92,016 10%
- Doors, windows and fittings Rs. 1,38,024 15%
- Flooring, plaster and paint Rs. 1,38,024 15%
- Electrical Rs. 73,612.80 8%
- Plumbing and sanitary Rs. 73,612.80 8%
Rates in this district run from Rs. 1,420 to Rs. 2,556 per sq.ft depending on the finish. Yours is Rs. 1,704.
Roughly what it takes
Site thumb rules on 540 sq.ft. Useful for checking a supplier's bill, not for ordering against.
216 bags
Cement
2,160 kg
Steel (TMT)
972 cft
Sand
729 cft
Aggregate
4,320 nos
Bricks
This is an estimate, not a quotation. It is worked out from Rs. 1,420 per sq.ft ×1.20 for standard finish. Soil, access, the shape of the plot and the market that month all move the real figure. Send it to us and we will price your actual plot.