House construction cost calculator
Put in the area, the floors and the finish. You get the rate, the split and the material.
Estimated cost to build
Rs. 20,43,522
Rs. 1,661.40 per sq.ft · 1,230 sq.ft built-up · Standard finish
Material
Rs. 16,13,022
Labour
Rs. 4,30,500
Floor by floor
| Level | Area | Rate factor | Cost |
|---|---|---|---|
| Ground floor | 615 sq.ft | ×1.00 | Rs. 10,47,960 |
| First floor | 615 sq.ft | ×0.95 | Rs. 9,95,562 |
| Total | Rs. 20,43,522 | ||
Where the money goes
Across the built work — Rs. 20,43,522. Lump sums like a lift or a borewell are listed above instead.
- Cement Rs. 3,26,963.52 16%
- Steel (TMT) Rs. 2,86,093.08 14%
- Sand Rs. 1,63,481.76 8%
- Aggregate Rs. 1,22,611.32 6%
- Bricks / blocks Rs. 2,04,352.20 10%
- Doors, windows and fittings Rs. 3,06,528.30 15%
- Flooring, plaster and paint Rs. 3,06,528.30 15%
- Electrical Rs. 1,63,481.76 8%
- Plumbing and sanitary Rs. 1,63,481.76 8%
Rates in this district run from Rs. 1,420 to Rs. 2,556 per sq.ft depending on the finish. Yours is Rs. 1,704.
Roughly what it takes
Site thumb rules on 1,230 sq.ft. Useful for checking a supplier's bill, not for ordering against.
492 bags
Cement
4,920 kg
Steel (TMT)
2,214 cft
Sand
1,660.50 cft
Aggregate
9,840 nos
Bricks
This is an estimate, not a quotation. It is worked out from Rs. 1,420 per sq.ft ×1.20 for standard finish. Soil, access, the shape of the plot and the market that month all move the real figure. Send it to us and we will price your actual plot.