House construction cost calculator
Put in the area, the floors and the finish. You get the rate, the split and the material.
Estimated cost to build
Rs. 21,93,048
Rs. 1,661.40 per sq.ft · 1,320 sq.ft built-up · Standard finish
Material
Rs. 17,31,048
Labour
Rs. 4,62,000
Floor by floor
| Level | Area | Rate factor | Cost |
|---|---|---|---|
| Ground floor | 660 sq.ft | ×1.00 | Rs. 11,24,640 |
| First floor | 660 sq.ft | ×0.95 | Rs. 10,68,408 |
| Total | Rs. 21,93,048 | ||
Where the money goes
Across the built work — Rs. 21,93,048. Lump sums like a lift or a borewell are listed above instead.
- Cement Rs. 3,50,887.68 16%
- Steel (TMT) Rs. 3,07,026.72 14%
- Sand Rs. 1,75,443.84 8%
- Aggregate Rs. 1,31,582.88 6%
- Bricks / blocks Rs. 2,19,304.80 10%
- Doors, windows and fittings Rs. 3,28,957.20 15%
- Flooring, plaster and paint Rs. 3,28,957.20 15%
- Electrical Rs. 1,75,443.84 8%
- Plumbing and sanitary Rs. 1,75,443.84 8%
Rates in this district run from Rs. 1,420 to Rs. 2,556 per sq.ft depending on the finish. Yours is Rs. 1,704.
Roughly what it takes
Site thumb rules on 1,320 sq.ft. Useful for checking a supplier's bill, not for ordering against.
528 bags
Cement
5,280 kg
Steel (TMT)
2,376 cft
Sand
1,782 cft
Aggregate
10,560 nos
Bricks
This is an estimate, not a quotation. It is worked out from Rs. 1,420 per sq.ft ×1.20 for standard finish. Soil, access, the shape of the plot and the market that month all move the real figure. Send it to us and we will price your actual plot.